SCHEDULED MAINTENANCE: SINGAPORE (AP3,AP9,SIN01) INFRASTRUCTURE MAINTENANCE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Jun 11, 2021 - 18:00 UTC
Update
Due to unforeseen circumstance change CHG0013997 will be extended by 1 hour to allow for completion of maintenance. No additional impact or risk is expected.
Posted Jun 11, 2021 - 16:54 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 11, 2021 - 12:00 UTC
Scheduled
Impact: No impact to clients is expected

Dear Client

On the date listed below engineers will be performing scheduled maintenance in the location listed below. This maintenance is necessary to perform upgrades to the storage infrastructure supporting the Cloud and Managed Hosting Services. During this maintenance we will be upgrading storage devices to the latest vendor approved and tested OS release. Although this type of maintenance has been performed in the past without impact, there is a low risk of latency and service disruption to Client Cloud and Managed Hosting Servers. The Admin UI/API and Community will remain available.

Change Reference Number: CHG0013997
Singapore (AP3, AP9,SIN01): Friday June 11th 9:00 PM Japan Standard Time (12:00 UTC)
Expected Total Duration: 5 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Jun 02, 2021 - 15:16 UTC
This scheduled maintenance affected: AP - Singapore (Managed Hosting SIN01, NTT Cloud AP3, CSfS AP9).